DA 26/0352 — 30 Douglas Road, Moss Vale
Wingecarribee Shire Council re-notified this Development Application on 29 July 2026, after the applicant lodged updated information. It is currently before the NSW Land and Environment Court (Nakar Property Unit Trust v Wingecarribee Shire Council).
What's proposed (per Council's notice)
A gas-powered electricity generation facility comprising seven (7) gas generator sets, and a battery energy storage system able to supply up to 30 megawatts (MW), plus associated works, access road, hardstand, lighting, security and stormwater infrastructure.
Exhibition period
31 July – 31 August 2026
How to lodge a submission
- Online, via Council's DA Tracker
- By email to mail@wsc.nsw.gov.au
- By post to PO Box 141, Moss Vale NSW 2577
Making your submission count
The applicant has revised their plans after Council's assessment report recommended refusal. Because the changes are substantial, every submission lodged during this re-exhibition period becomes part of the evidence before the Land and Environment Court.
To make your submission count:
- Tell us who you are. A sentence or two on how this affects you, your family, your business or your health. Personal accounts carry real weight in these proceedings.
- Pick 2–4 topics from the list below that matter most to you.
- Use our full guide for the detail behind each one — reword it in your own words, or paste it in directly.
- Lodge before 5pm, Monday 31 August 2026, using the options above.
Grounds you can raise
- Battery size and safety checks — The 30 MW battery is described as a minor building extension rather than a standalone facility, which may avoid the independent safety and fire checks a battery this size would otherwise require.
- State pollution limits — The physical generating capacity on site appears to exceed the threshold that triggers a mandatory EPA pollution licence.
- Splitting the project into smaller DAs — This application is being assessed separately from a much larger 673 MW proposal on the same site, which may prevent decision-makers from seeing the full combined impact.
- Moving the creek & flood risk — The plans involve realigning a natural watercourse for the battery platform, without the flood modelling Council's engineers say is required.
- Bushfire risk — Council and the NSW Rural Fire Service have identified the site as bushfire-prone land, contrary to the applicant's own assessment.
- Water use & Sydney's drinking water — Water use figures appear to cover only staff amenities, not the cooling and operational needs of the wider data campus, on a site within Sydney's drinking water catchment.
- Exhaust stack heights — At 23.5 metres, the proposed stacks exceed both the local Development Control Plan height limit and the Innovation Park masterplan limit.
- Train line safety — The site is located near an active rail corridor, and the required rail safety assessment doesn't appear to have been submitted.
- 24/7 noise & low-frequency hum — Continuous engine operation may carry noise toward homes in Burradoo and Moss Vale, and toward the Garvan Institute's nearby medical research facility.
- Night security lighting — Round-the-clock lighting is planned, but no lighting or light-spill assessment appears to have been submitted, despite Council raising it.